Upper Thames Street,
London EC4
Requiring the completion of a
multi storey apartment block following the demise of the Main
Contractor this project was undertaken for Riverview Holdings.
Commencing on site within two
weeks of being approached by the Client, Axiom were not only able to
complete a number of incomplete apartments, common areas, envelope
works and basements but also deal with a multitude of tenant
defects, outstanding works and certifications.
This 20 week project not only
required intense management and programming but also close liaison
with the building occupants and the Clients team in order to finally
bring this project to a close.